Avista Selects Projects for New Energy and Capacity Resources along with Demand Response
Avista’s 2025 Electric Integrated Resource Plan (IRP) filed on
To meet these needs, Avista will begin contract negotiations for the following projects:
- A self-build upgrade of Avista’s existing Natural Gas Combustion Turbines in north
Idaho to add 14 MW of capacity without increasing carbon emissions. This upgrade will occur in two stages with the first occurring in 2027 and the second in 2029. - A project for 100 MW, 4-hour Battery Energy Storage System (BESS), to be built and transferred to Avista in eastern
Washington with a target date in 2028. - A Power Purchase Agreement for approximately 200 MW of wind power from
Montana that utilizes the Avista share of the Colstrip Transmission System with a target date in 2029. - The addition of approximately 40 MW of Demand Response Programs that will recruit residential, commercial and industrial customers within Avista’s service territory, beginning in 2026.
“We are encouraged by the projects selected as a part of this process and the value they represent. The resources that were selected will play a critical role in meeting reliability and resource adequacy goals to serve customers and the growing demand for energy,” said
Avista’s RFP solicited proposals from bidders across all technology types, including demand response, to secure additional energy and capacity which would support long-term resource adequacy and reliability needs identified in the 2025 IRP.
More information about the selected projects will be provided as contracts become final. Additional information related to the RFP is available on the Avista website at www.myavista.com/allsourcerfp.